GRUPOTEC was awarded this project in the renewable energy auction in Spain (2017). Developed entirely by the company itself, it is the second project in which GRUPOTEC has invested within a plan that plans to build 500 MW in three years. Construction work has started, which will conclude during 2019.
After closing the financing of the project, obtaining the administrative authorizations and completing the engineering, GRUPOTEC now undertakes the construction works on the ground, which include:
– Photovoltaic generation plant, 50 MWp with one axis tracker.
– Lifting substation (30kV- 132 kV)
– High voltage power line (132 kV), with low pass for the AVE line.
– Estimated production: 107,000 MWh / year (enough for 41,300 homes).
Compartir