It is a project hosted at the last auction of the Spanish administration and developed by the company itself. The project is GRUPOTEC’s first investment within the framework of a growth plan that plans to build 500 MW in Spain in the next three years.
After closing the financing of the project and obtaining all the administrative authorizations, GRUPOTEC now undertakes the construction work on the ground, both for the photovoltaic plant and the lifting substation and the high voltage 132 kV power lines.
These construction works will be carried out throughout 2019 to install a total power of 41.6 MW on a single axis tracker and an estimated production of 85,000 MWh per year, which represents the generation necessary to supply green energy to a population of 25,000 homes.